See update below dated 7/7/14. Q. What are Albany Unified School District’s (AUSD’s) planned Summer 2014 Facilities Projects? A. 1) Albany High School Remodeling; 2) Mac Gregor High School Demolition; 3) Albany Middle School modular classroom(s) installation; 4) Ocean View Elementary School modular classroom installation, 5) Marin Elementary School modular classroom installation; and 6) Cornell Elementary School modular classroom installation. (see PDF below)


Facilities Summer Projects Update

July 7, 2014



Facilities Summer Projects Update: 7/7/14


AHS

The remodeling projects at Albany High School are substantially underway and will be completed by 8/11/14. 

 

AMS

The portables at Albany Middle School are being installed on Tuesday, 7/8 and Wednesday, 7/9. They are on schedule and will be ready by the time staff returns in August.

 

MacGregor

MacGregor has been cleared of all furniture and other items that are salvageable.  We anticipate the demolition to be completed by August 22nd.

 

Elementary Site Portables

The portables being installed on each of the elementary campuses are on schedule to be installed starting on 7/10. They will all be set by 7/11 when the other work will commence (electricity, PA and fire alarm system). This project will be complete by the second week of August before staff returns.